Project Timeline
(all dates italicized are projected; the schedule will be updated as dates are confirmed):
Pre-Design Phase:
CEREMONIAL GROUNDBREAKING - 4/22/2008
Schematic Design Phase:
- Schematic Design Approval - 12/2008
Design Phase:
- DENR Building Design Approval - 9/2009
- NRC Building Design Approval - 12/2009
Construction Phase:
- Foundation/Underground Parking Start - 3/2009
- Foundation Complete - 2/2010
- Construction Mobilization DENR Building - 11/2009
- Construction Mobilization NRC Building - 2/2010
- Project Completion DENR Building - Spring 2011
- Project Completion NRC Building - Fall 2011